Yes, but there are conditions. The current net-metering rules allow for meter aggregation if:
- The meters are under common ownership;
- The meters are located in Arkansas Valley Electric Cooperative’s service area;
- The customer must give at least 30 days’ notice to AVECC to complete the request;
- If more than one additional meter is identified, the customer must designate the rank order (no more than once every year) for the meters to which net excess generation is to be applied;
- Net excess generation shall first be credited to the net-metering customer’s generation meter;
- Any remaining net excess generation shall be credited to one or more of the customer’s additional meters in the rank order provided by the customer.
- A generation meter can offset usage for multiple additional meters. However, a generation meter cannot offset usage from another generation meter. In other words, an additional meter’s usage cannot be offset by multiple generation meters.