Step 1: Review the Arkansas Public Service Commission’s Net-Metering Rules.
Step 2: Complete the Application for Preliminary Interconnection and Site Review Request. The applications should include a detailed electrical diagram and specifications of the equipment used. AVECC will review the submitted application and respond in writing within 30 calendar days. Email the completed application to netmetering@avecc.com or mail to 208 South 17th Street, Ozark, AR 72949.
Step 3: At least 30 days prior to connecting, submit the standard interconnection agreement for net-metering Facilities.
Step 4: Once the install is completed, the net-metering owner must submit a complete inspection report from a qualified person. The inspector must be qualified by one of the three requirements below: State Inspector City Inspector Qualified Independent Contractor The Independent inspector must meet the following requirements: I. Licensed and qualified Contractor and Master Electrician in the State of Arkansas II. Independent of the Owner or operator of the facility III. Independent of the Solar Company and/or Installer who completed the installation and verified Section 3 of the Interconnection Agreement.
Step 5: AVECC will schedule a site visit to swap the meter and commission the system. The net-metering facility must be left disconnected and out of service until the site visit from AVECC.
Step 6: Upon approval, the standard interconnection agreement will be signed by AVECC, and the account will be set up for net metering.